    Ten MVP (Most Valuable Personal) Traits of Successful Entrepreneurs
    Since beginning my own entrepreneurial ventures in 1982, I have observed much and learned much about what is behind the success of entrepreneurs. I have selected a number of those traits and call them Ten MVP, or Most Valuable Personal, traits of successful entrepreneurs. The selected traits shown below reflect my opinion from personal observation and are not listed in priority order.+ Trait #1: Positive, persistent and passionate – The truly successful entrepreneur is intense and has a personal passion to change things. The successful entrepreneur does not mind devoting more than 12 hours a day to his
    e the measure from 265 days to 30 days in six weeks. Then to reduce it 25 days in six months and to reduce it to twenty days in twelve months.

    They achieved their targets and we achieved some interesting results. Our in-stock levels increased from 82% to 93%, our customer and distributor complaints dropped to zero, our levels of returns reduced from thirty pallets a week to two, our congested loading dock freed up, our completed delivery rate went up, our space requirement for holding stock reduced by forty percent.

    Customers were happier, employees could complete a job without passing blame and you guessed it, productivity went up.

    Concentrating on productivity had forced our employees to concentrate on long run, low set up cost, products. Low run and high set up cost "speciality" grades were not filled. This resulted in high stock outs, long back orders and when we finally did get stock, high lev

    Management By Objective (MBO) - How to Use this Technique For Practical Management Results
    Management By Objective (MBO)A Time Tested Management Method Classic That Works – With the Right PeopleManagement by Objective (MBO) is the basic “blocking and tackling” of management. It is simple, effective and can be used to some degree with most people who have some capability for forethought. Unfortunately this is not everyone. Here is a simple step-by-step description of how to use this powerful classic management method, which should be in every manager’s repertoire. It doesn’t always work for everyone; as the book Good to Great says, “you have to have the right people on the bus,” as no
    Organisations measure what they value: volume, profit, safety, errors, customer or employee satisfaction.They measure what they hope to influence.

    Problems arise for organisations when they substitute proxy measures for what they value that are not actually directly related to what they value.

    A personal example of this was when I was a production manager in charge of a lubricating oil plant in Sydney, Australia.

    What the organisation I worked for valued was profit before tax, which was duly measured. Other measures which received air time were customer satisfaction, employee satisfaction and safety.

    At an operational level we had a fixation on costs and as a driver of costs, labour productivity. We fought for a long while to get productivity accepted by the unions as a legitimate measure that influenced their take home pay.

    The performance of our plant at which I was a supervisor at the time was illustrated by continual stock outs, long back orders, high levels of obsolete stock, despatch areas congested with returned stock, poor customer satisfaction and overall productivity one quarter of the national average.

    We were, as a supervisory group, considered by our senior managers, marketing colleagues and distributors to be incompetent.

    We finally succeeded in negotiating a wage case including productivity as a yardstick of performance. We went about setting productivity targets for blending oil expressed in litres blended per man hour, filling oil expressed in packages per man hour for every package size and warehousing expressed in litres per man hour moved in and out of the warehouse.

    We expected that by concentrating on productivity in this manner, productivity would rise, costs would drop and our ability to supply the market would increase dramatically. We told our marketing colleagues and distributors to expect better times.

    Initially, productivity rose, costs declined and customer service levels improved slightly. However, the improvement was nothing like what we expected and after a year or so, the results started to decline. We redoubled our efforts looking at the drivers of productivity.

    Still the improvements did not come as we expected.

    At this time I was transferred to a plant in Brisbane, returning eighteen months later as the manager of the Sydney plant. The time away had not changed the statistics; we were still poor at what we did. Our concentration on productivity had failed to deliver on what the organisation valued.

    Eighteen being months production manager at a plant which had the highest level of productivity in the country allowed me time to think and observe what drove people and what demonstrated that manufacturing plants were functioning from a customer's point of view and what measures at a plant level influenced what the organisation valued.

    Note: the reason I had time to think in Brisbane is that the guys running the plant did it so well, there was not a lot to manage.

    I made a decision upon my return to Sydney to no longer measure labour productivity. We would measure instead, the number of days it took us to bring the stock level of a stock keeping unit back above its reorder point level after it had fallen below the level. The measure we would report was our worst open case. That measure at the time stood at 265 days.

    That meant we had not replenished the stock on one of the stock keeping units for 265 days even though our stock levels were built on satisfying customer demand with a maximum of twenty days replenishment cycle.

    The whole of the production team, supervisors, clerks and storemen were given the challenge to reduce the measure from 265 days to 30 days in six weeks. Then to reduce it 25 days in six months and to reduce it to twenty days in twelve months.

    They achieved their targets and we achieved some interesting results. Our in-stock levels increased from 82% to 93%, our customer and distributor complaints dropped to zero, our levels of returns reduced from thirty pallets a week to two, our congested loading dock freed up, our completed delivery rate went up, our space requirement for holding stock reduced by forty percent.

    Customers were happier, employees could complete a job without passing blame and you guessed it, productivity went up.

    Concentrating on productivity had forced our employees to concentrate on long run, low set up cost, products. Low run and high set up cost "speciality" grades were not filled. This resulted in high stock outs, long back orders and when we finally did get stock, high leve

    The Weaker Sex Can Pack A Mean Business Punch Too!
    Judging from the title itself, you’re probably expecting a men-bashing article about the kind of injustice that men cause women and about how women should learn how to hold their can of pepper spray in hand (facing the right direction, of course, unless the women plan to blind themselves) the moment they catch a whiff of a MAN.Well….er, no. Not really.I am here to explain and give some good examples of why and how women can do what they want to do in business and reap full benefits of the structure that they have chosen to adopt. I want to encourage them and tell them that women can make good busine
    e time was illustrated by continual stock outs, long back orders, high levels of obsolete stock, despatch areas congested with returned stock, poor customer satisfaction and overall productivity one quarter of the national average.

    We were, as a supervisory group, considered by our senior managers, marketing colleagues and distributors to be incompetent.

    We finally succeeded in negotiating a wage case including productivity as a yardstick of performance. We went about setting productivity targets for blending oil expressed in litres blended per man hour, filling oil expressed in packages per man hour for every package size and warehousing expressed in litres per man hour moved in and out of the warehouse.

    We expected that by concentrating on productivity in this manner, productivity would rise, costs would drop and our ability to supply the market would increase dramatically. We told our marketing colleagues and distributors to expect better times.

    Initially, productivity rose, costs declined and customer service levels improved slightly. However, the improvement was nothing like what we expected and after a year or so, the results started to decline. We redoubled our efforts looking at the drivers of productivity.

    Still the improvements did not come as we expected.

    At this time I was transferred to a plant in Brisbane, returning eighteen months later as the manager of the Sydney plant. The time away had not changed the statistics; we were still poor at what we did. Our concentration on productivity had failed to deliver on what the organisation valued.

    Eighteen being months production manager at a plant which had the highest level of productivity in the country allowed me time to think and observe what drove people and what demonstrated that manufacturing plants were functioning from a customer's point of view and what measures at a plant level influenced what the organisation valued.

    Note: the reason I had time to think in Brisbane is that the guys running the plant did it so well, there was not a lot to manage.

    I made a decision upon my return to Sydney to no longer measure labour productivity. We would measure instead, the number of days it took us to bring the stock level of a stock keeping unit back above its reorder point level after it had fallen below the level. The measure we would report was our worst open case. That measure at the time stood at 265 days.

    That meant we had not replenished the stock on one of the stock keeping units for 265 days even though our stock levels were built on satisfying customer demand with a maximum of twenty days replenishment cycle.

    The whole of the production team, supervisors, clerks and storemen were given the challenge to reduce the measure from 265 days to 30 days in six weeks. Then to reduce it 25 days in six months and to reduce it to twenty days in twelve months.

    They achieved their targets and we achieved some interesting results. Our in-stock levels increased from 82% to 93%, our customer and distributor complaints dropped to zero, our levels of returns reduced from thirty pallets a week to two, our congested loading dock freed up, our completed delivery rate went up, our space requirement for holding stock reduced by forty percent.

    Customers were happier, employees could complete a job without passing blame and you guessed it, productivity went up.

    Concentrating on productivity had forced our employees to concentrate on long run, low set up cost, products. Low run and high set up cost "speciality" grades were not filled. This resulted in high stock outs, long back orders and when we finally did get stock, high lev

    Job Interviews - What You Don't Do Can HELP You!
    I just love job performance evaluations. Where else can you say things like“Since my last evaluation, this employee has hit bottom and started to dig.”“His team would follow him anywhere, but only out of morbid curiosity.”“This employee would be out of her depth in a parking lot puddle.”“She works well when under constant supervision and cornered like a rat in a trap.”Luckily, none of these statements were made BY or ABOUT me, but I’ve often wondered why those employees were hired in the first place. Was there no clue to their cluelessness BEFORE they were hired – like during
    colleagues and distributors to expect better times.

    Initially, productivity rose, costs declined and customer service levels improved slightly. However, the improvement was nothing like what we expected and after a year or so, the results started to decline. We redoubled our efforts looking at the drivers of productivity.

    Still the improvements did not come as we expected.

    At this time I was transferred to a plant in Brisbane, returning eighteen months later as the manager of the Sydney plant. The time away had not changed the statistics; we were still poor at what we did. Our concentration on productivity had failed to deliver on what the organisation valued.

    Eighteen being months production manager at a plant which had the highest level of productivity in the country allowed me time to think and observe what drove people and what demonstrated that manufacturing plants were functioning from a customer's point of view and what measures at a plant level influenced what the organisation valued.

    Note: the reason I had time to think in Brisbane is that the guys running the plant did it so well, there was not a lot to manage.

    I made a decision upon my return to Sydney to no longer measure labour productivity. We would measure instead, the number of days it took us to bring the stock level of a stock keeping unit back above its reorder point level after it had fallen below the level. The measure we would report was our worst open case. That measure at the time stood at 265 days.

    That meant we had not replenished the stock on one of the stock keeping units for 265 days even though our stock levels were built on satisfying customer demand with a maximum of twenty days replenishment cycle.

    The whole of the production team, supervisors, clerks and storemen were given the challenge to reduce the measure from 265 days to 30 days in six weeks. Then to reduce it 25 days in six months and to reduce it to twenty days in twelve months.

    They achieved their targets and we achieved some interesting results. Our in-stock levels increased from 82% to 93%, our customer and distributor complaints dropped to zero, our levels of returns reduced from thirty pallets a week to two, our congested loading dock freed up, our completed delivery rate went up, our space requirement for holding stock reduced by forty percent.

    Customers were happier, employees could complete a job without passing blame and you guessed it, productivity went up.

    Concentrating on productivity had forced our employees to concentrate on long run, low set up cost, products. Low run and high set up cost "speciality" grades were not filled. This resulted in high stock outs, long back orders and when we finally did get stock, high lev

    Acting - Finding Your Perfect Agent
    The most important step before attempting to pick an agent is to decide what you're looking for. Look at your resum? and see what kind of experience you have and the type of work you'd be looking for. Understanding these issues will make it much easier for you to decide which agent best fits your ambitions and talents. Realize that very few actors spend their entire careers with one agent, so as your career changes, so too might your agent.Research is the key to finding an agent that suits your needs. There are many different questions to consider, such as: are they representing extras or principal rol
    a customer's point of view and what measures at a plant level influenced what the organisation valued.

    Note: the reason I had time to think in Brisbane is that the guys running the plant did it so well, there was not a lot to manage.

    I made a decision upon my return to Sydney to no longer measure labour productivity. We would measure instead, the number of days it took us to bring the stock level of a stock keeping unit back above its reorder point level after it had fallen below the level. The measure we would report was our worst open case. That measure at the time stood at 265 days.

    That meant we had not replenished the stock on one of the stock keeping units for 265 days even though our stock levels were built on satisfying customer demand with a maximum of twenty days replenishment cycle.

    The whole of the production team, supervisors, clerks and storemen were given the challenge to reduce the measure from 265 days to 30 days in six weeks. Then to reduce it 25 days in six months and to reduce it to twenty days in twelve months.

    They achieved their targets and we achieved some interesting results. Our in-stock levels increased from 82% to 93%, our customer and distributor complaints dropped to zero, our levels of returns reduced from thirty pallets a week to two, our congested loading dock freed up, our completed delivery rate went up, our space requirement for holding stock reduced by forty percent.

    Customers were happier, employees could complete a job without passing blame and you guessed it, productivity went up.

    Concentrating on productivity had forced our employees to concentrate on long run, low set up cost, products. Low run and high set up cost "speciality" grades were not filled. This resulted in high stock outs, long back orders and when we finally did get stock, high lev

    Develop Loyal Customers for a Lifetime - part 2 (11 - 20)
    Traditional marketing strategies encourage business owners to continually grow their businesses by adding new customers. In today's competitive world of business, it is more important than ever to aim for more transactions with existing customers by using the power of customer follow-up and attention to good service.These second ten tips will help you in turning your existing customers into walking billboards for your business and loyal customers for a lifetime. While we aren't advocating that you do all ten, choosing your favorite five and making sure they become a part of your marketing efforts will pa
    e the measure from 265 days to 30 days in six weeks. Then to reduce it 25 days in six months and to reduce it to twenty days in twelve months.

    They achieved their targets and we achieved some interesting results. Our in-stock levels increased from 82% to 93%, our customer and distributor complaints dropped to zero, our levels of returns reduced from thirty pallets a week to two, our congested loading dock freed up, our completed delivery rate went up, our space requirement for holding stock reduced by forty percent.

    Customers were happier, employees could complete a job without passing blame and you guessed it, productivity went up.

    Concentrating on productivity had forced our employees to concentrate on long run, low set up cost, products. Low run and high set up cost "speciality" grades were not filled. This resulted in high stock outs, long back orders and when we finally did get stock, high levels of returns from customers who had gone to competitors to get their order filled.

    Concentrating on operating our plant to a plan to satisfy customer orders and improve customer satisfaction kept the focus on delivery to customers, one of the outcomes the organisation valued.

    We became what we measured.

    HTTP = HTML link (for blogs, profiles,phorums):
    <a href="http://www.added4u.com/article/22212/added4u-Measuring-the-Right-Indicator-to-Drive-Behaviour.html">Measuring the Right Indicator to Drive Behaviour</a>

    BB link (for phorums):
    [url=http://www.added4u.com/article/22212/added4u-Measuring-the-Right-Indicator-to-Drive-Behaviour.html]Measuring the Right Indicator to Drive Behaviour[/url]

    Related Articles:

    When the Job Search is Over, be Sure to Say Thanks

    Defusing Customer Disputes: 7 Strategies to Centered Communication

    Leadership and Tony Soprano

    Bookmark it: del.icio.us digg.com reddit.com netvouz.com google.com yahoo.com technorati.com furl.net bloglines.com socialdust.com ma.gnolia.com newsvine.com slashdot.org simpy.com shadows.com blinklist.com